This email is to notify you that works will be commencing shortly at Rosedale Park Road (from jack Hinton Drive to Paul Matthews Road).
Construction is scheduled to start on Monday 13/05/2024 and will take approximately 10 weeks.


The scope of work includes:
- Installation of height barriers.
- New road platform on the road section opposite to the club office with a different colour profile.
- Installation of planter boxes on the centre medium of the road section opposite to the club office.
- Installation of road humps at suitable locations.
- Installation of appropriate sign boards.
- Fixing of road damaged section at suitable locations.
Physical works will be carried out by Auckland Civil Limited – Contact: Steve Taylor M: 0274 825 675
Project Design Consultant : Stellar Projects – Kyle Kaliniak -M: 022 696 1980
Auckland Council Project Manager,Mahesh Dharmaratne – M: 027 211 4182.